APPLICATIONS - Chemical / Pharmaceutical / Cosmetic / Paint
Envochem® COL Waste water from bromine extrac-tion and fabrication of bromine containing intermediate products
The treatment plant is designed for a flow rate of 150 m³/h. The water is treated by the following procedure steps:
- coarse screening for the removal of solids > 8 mm
- separation of heavy and light solvents
- two-step flow neutralization
- flocculation Envochem® COL
- sedimentation of suspended solids
- dehydration of suspended solids
- treatment of the drawing-off air out of the various tanks
Performance
| Envochem® COL: | |
| capacity | 150m³/h |
Physico/chemical data
| before treatment | after treatment | |
| pH | 1-2 | approx. 7 |
| AlCl3 | 1400 mg/l | 1 mg/l |
| heavy and | ||
| light solvents | 100-1000 mg/l | none |
for further information
Bromine_0107.pdf (186.93 kb)
Contact
plants.engineering(at)envirochemie.com
Tel: +49 (0) 61 54 / 69 98 - 0